Category

KNS

The official inauguration of Koniambo Nickel

François Hollande, The President of the French Republic visited the Northern Plant on Monday November 17, 2014, joined by George Pau-Langevin, Minister of Overseas, Paul Néaoutyine, President of the Northern Province, Ivan Glasenberg, Chief Executive Officer, Glencore, André Dang Van Nha, President, SMSP, Peter Hancock, President, Koniambo Nickel and Vincent Bouvier, High Commissioner of the...

Koniambo Nickel recruitment campaign

Koniambo Nickel launched a major recruitment campaign to fill the technical positions needed for the operational phase of its pyrometallurgical plant. 150 posts are published in different sectors: mechanical workshop, mechanical fixed installations, mechanical mobile machinery, industrial electricity and power supply, mine and plant operations, engineering / industrial design, building maintenance, geology and mineral processing,...

Last major step in the successful commissioning phase of the Northern Plant

KNS has successfully processed this day Saturday, February 8, 2014 at 5:30 pm the first nickel tapping of the second production line of its metallurgical plant. With five days ahead of the schedule set, this milestone crowns the commissioning phase of the second production line. All facilities of the metallurgical plant have now successfully passed...

End of the construction of the second line of production

The construction of the second production line of the Northern Plant is now achieved. This implies the demobilization of the staff and equipment affected to the construction and launches the commissioning phase. The demobilization will continue throughout 2014 to end up in December 2014 with the last step, the closed down of the camp.

The French Prime Minister Jean-Marc Ayrault visited the Northern Plant

The Prime Minister attended a nickel‘s casting performance at the Northern Plant on 27th July 2013. He was accompanied by an important delegation including Victorin Lurel, Minister of Overseas Territories, Fleur Pellerin, Deputy Minister of innovation and small & medium companies, Jean-Jacques Brot, High Comissionner of the French Republic in New Caledonia, Philippe Gomes Member...

Celebration of the Northern Plant’s first nickel tapping

A special celebration of the Northern Plant’s first nickel tapping was convened on Friday, April 19, with the presence of the State and Government representatives, the Northern Province’s President as well as SMSP’s and Xstrata’s representatives. The program began with a guests’ welcome ceremony, performed by the Northern Plant’s President, Peter Hancock, before the participants...

First metal tapping of the Northern Plant

The Northern Plant achieved its first metal tapping on the 10th April 2013 at 8:35 pm. This tap came after the first slap tapping achieved at 12:55 pm the same day. The electrical furnace, pre-loaded with 230 tons of steel, has been gradually heated to approximately 1,000 degrees Celsius temperature for the constitution of the...

The 21th Koniambo Committee was held in Koné on the 15th of March 2013

During this committee KNS has presented the general advancement of the project (including healthy, safety & environmental issues, work in progress of the construction, commissioning of the first line, human resources) while the Cellule Koniambo unit has presented the current situation on the demobilization of subcontractors working and the organization of CGE VKP.

First tapping of the Northern Plant scheduled for March

Following the Line 1 furnace heat up during February 2013, the first metal bath tapping is expected to take place by the end of March, in line with the commissioning and ramp up plans. The plant is well positioned to deliver the two-year production ramp up to achieve its nameplate 60,000 tonnes of nickel in...

One more step in the start of the Northern Plant

Tuesday, February 5 at 3pm, the grinding/drying process of ore began with some tests, carried out on the ore preparation unit. These tests were performed with 20 tons of wet ore in order to check the overall equipment process including the crushing and drying mill, the separator, filters, the hot gas generator, the transport system...
1 2 3 4