First metal casting for KNS Furnace N°1 after its reconstruction

Wednesday, January 20, 2016 at 14:30 the Koniambo Nickel’s Team conducted the first casting of Furnace n°1, after its rebuilding, during which operation 45 tons of ferronickel were produced on the Vavouto Industrial Site. The Furnace n°1 was shut down in 26 December 2014, due to a molten metal leakage. After investigations, the Koniambo Nickel...