Last major step in the successful commissioning phase of the Northern Plant

KNS has successfully processed this day Saturday, February 8, 2014 at 5:30 pm the first nickel tapping of the second production line of its metallurgical plant. With five days ahead of the schedule set, this milestone crowns the commissioning phase of the second production line. All facilities of the metallurgical plant have now successfully passed...